Behavior documentation

In Artelys Crystal Super Grid, most of the technologies have several modelling variations, also called “behaviors”. In order to activate one or the other variation of the model, the user may select the wanted behaviors for each asset via the Parameter tables.

The possible behaviors depend on the current technology and context type (for example, OPTIM_PMAX is only available for technologies that have a PMAX attribute, and in capacity optimization contexts).

The complete list of possible behaviors is available here:

ID Label Compatible context types
CLUSTER Enables cluster modelling for this asset (linearisation of startup and running costs ) OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
CONSTANT_VAR Force constant a temporal variable OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
DCOPF Enable a Direct Current Optimal Power flow approach OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
DISCHARGE_TIMES Enables the definition of the storage capacity with a discharge time (storage capacity = discharge time * max generation) OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
EQUALITY_CONSTRAINT Changes the minimum RES generation constraint into an equality constraint OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
FLOW_BASED Includes the selected transmission into flow-based market coupling constraints PATHWAY_SIMULATION, SIMULATION
FUEL Activates the explicit modelling of the fuel consumption of the asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
GAS_BACKUP_HEATER Use a gas backup heater (instead of an electric back-up) in the heat pump asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
GRADIENTS Enables gradient constraints for this asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
MFRR_DOWN Enables the participation to downward mFRR of the DSR asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
MFRR_UP Enables the participation to upward mFRR of the DSR asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
MUST_RUN Forces the asset to produce up to its availability (must run energy source) OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
OPTIM_PATHWAY Enables optimization of the capacity of the asset during pathway optimization PATHWAY_OPTIM
OPTIM_PMAX Enables the economic optimisation of the capacity of this asset OPTIM_CAPA
REPOWERING Enables repowering of the asset during pathway optimization PATHWAY_OPTIM
RESERVE Enables reserve allocation modelling for this asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
RETROFIT_CCS Enables CCS asset retrofitting OPTIM_CAPA, PATHWAY_OPTIM
RETROFIT_H2 Enables asset retrofitting to hydrogen OPTIM_CAPA, PATHWAY_OPTIM
SYNC_RESERVE_DOWN Enables the participation to downward synchronized reserve of the DSR asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
SYNC_RESERVE_UP Enables the participation to upward synchronized reserve of the DSR asset OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
UNIT Enables Unit Commitment modelling (binary variables to describes asset states, startup and shutdown costs, minimal state durations and variable yields) OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
USE_ENERGY_PRODUCTION Enables vehicle to grid production OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
USE_PMAX_IN Enables the definition of an input power capacity (pmaxIn) different from the generation capacity (Pmax) OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM
VOLUME_TARGET Force a minimum or maximum volume of export/import OPTIM_CAPA, PATHWAY_SIMULATION, SIMULATION, PATHWAY_OPTIM